CTEC Team Ensured HYH Unit 1 HFT Success

 [2012-07-06]

 

          At 15 pm on July 4th, Unit 1 of Hong Yan-he nuclear power station successfully finished its hot functional test (HFT), which was another key milestone completed of the project. 

          CTEC's project team working at the forefront overcame the difficult field conditions with great enthusiasm for the work. They ensured the smooth progress of the HFT with the faith of customer first and obtained the recognition of the owner and the contractor's commissioning team.

 