CTEC Completed ND Unit 1 DCS Upgrade

[2014-04-30]

On Apr 29th, the equipment upgrade during the first refueling outage of Ningde NPP Unit 1 was successfully completed. CTEC had an outstanding performance in the DCS upgrade process.

It took CTEC 51 days to finish the DCS upgrade work. CTEC project team made the work plan half a year ahead and provided around-the-clock response to emergency on site. Their efforts was paid back a completion time of 4.5 hours earlier than the plan and a minimum unavailable time of KIC, which received high praise from the plant owner.

 