YJ Unit 1 First Refueling Overhaul DCS Upgrade Finished

 [2015-04-14]

On Apr 14th, CTEC CPR1000 project steam finished the DCS upgrade in the 1st refueling overhaul period for Yangjiang Unit 1 after 76 days’ hard work.

As for this upgrade task, CTEC took over the whole plan work and system design of both the safety and non-safety DCS, as well as the hardware upgrade, testing and field technology support work. During the Spring Festival, CTEC’s engineers working on site even gave up their vacation. They stuck to their jobs with enthusiasm and dedication. Their effort and performance was highly recognized and appreciated by the customer.