Yangjiang Unit 6 Had its LOT1 DCS Equipments Delivered

[2016-04-11]

On April 11th, the LOT1 DCS equipments of Yangjiang Unit 6 passed the factory acceptance test (FAT) with no non-conforming report (NCR). They were delivered to the site soon. Up to now, for Yangjiang Unit 5, the LOT2 DCS equipments were being carrying out DF2 factory test and LOT3 equipments were about to complete the assembly. The LOT2 DCS equipments of Yangjiang Unit 6 have finished the engineering design and an ongoing assembly was carrying out at the moment.